The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c

🎲 Try a Random Question  |  Total Questions in Quiz: 150  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Construction Management — practice the complete quiz, review flashcards, or try a random question.


1. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c