Draw the precendence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships. What is the critical path duration for the given schedule network?

🎲 Try a Random Question  |  Total Questions in Quiz: 518  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CA0-001 PMI Practice Test — practice the complete quiz, review flashcards, or try a random question.


Draw the precendence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships. What is the critical path duration for the given schedule network?