When you are developing the estimates for the project, you choose to add the individuals estimates for the activities that comprise each phase. What type of estimation method are you using?

🎲 Try a Random Question  |  Total Questions in Quiz: 518  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CA0-001 PMI Practice Test — practice the complete quiz, review flashcards, or try a random question.


When you are developing the estimates for the project, you choose to add the individuals estimates for the activities that comprise each phase. What type of estimation method are you using?