If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

🎲 Try a Random Question  |  Total Questions in Quiz: 368  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CAPM Practice Exam — practice the complete quiz, review flashcards, or try a random question.


If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?