Bidder A wrote its proposal as follows: 'First Class Bricks --- 50,000 @ Rs 6,500 per thousand = Rs 225,000' In the bid evaluation the adjusted/corrected price would be:

🎲 Try a Random Question  |  Total Questions in Quiz: 47  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Civil Engineering (Construction Management) Practice Test Questions — practice the complete quiz, review flashcards, or try a random question.

Construction management involves planning, budgeting, coordinating, and supervising construction projects from start to finish.
 

The 6 main stages of a typical construction project are: pre-construction, sitework, rough framing, exterior construction, MEP (mechanical, electrical, and plumbing), and finishing.


Bidder A wrote its proposal as follows: 'First Class Bricks --- 50,000 @ Rs 6,500 per thousand = Rs 225,000' In the bid evaluation the adjusted/corrected price would be: