12 men take 36 days to do a work while 12 women complete 3/4 in of the same work in 36 days. In how many days 10 men and 8 women together will complete the same work?

🎲 Try a Random Question  |  Total Questions in Quiz: 45  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Time and Work — practice the complete quiz, review flashcards, or try a random question.


12 men take 36 days to do a work while 12 women complete 3/4 in of the same work in 36 days. In how many days 10 men and 8 women together will complete the same work?