The load on a hydel plant varies from a minimum of 10,000 kW to a maximum of 35,000 kW. Two turbo-generators of capacities 20,000 kW each have been installed. Calculate Plant factor.

🎲 Try a Random Question  |  Total Questions in Quiz: 58  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Irrigation Engineering Practice Test: Hydro Electric Power — practice the complete quiz, review flashcards, or try a random question.

Hydro Electric Power topics include: Thermal and hydropower, water power development, hydro electric scheme components, hydro electric power turbines types and their selection. Hydroelectric power, also known as hydropower, is a renewable energy source that uses the kinetic energy of moving water to generate electricity.  Hydropower plants are typically located near a water source. The amount of available energy in moving water is determined by the volume of the water flow and the change in elevation.  Hydropower plants use dams or diversion structures to create an elevation difference... Show more

The load on a hydel plant varies from a minimum of 10,000 kW to a maximum of 35,000 kW. Two turbo-generators of capacities 20,000 kW each have been installed. Calculate Plant factor.