If the schedule Variance (SV) = $55, and the Planned Value (PV) = $11, What is the earned Value (EV)?

🎲 Try a Random Question  |  Total Questions in Quiz: 518  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CA0-001 PMI Practice Test — practice the complete quiz, review flashcards, or try a random question.


If the schedule Variance (SV) = $55, and the Planned Value (PV) = $11, What is the earned Value (EV)?