The project budget is set at $150,000. The project Duration is planned be one year. At the completion of week 16 of the project, the following information is collected Actual cost $50,000 Plan cost $45,000 Earned Value $40,000 What is the cost performance index

🎲 Try a Random Question  |  Total Questions in Quiz: 518  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CA0-001 PMI Practice Test — practice the complete quiz, review flashcards, or try a random question.


The project budget is set at $150,000. The project Duration is planned be one year. At the completion of week 16 of the project, the following information is collected Actual cost $50,000 Plan cost $45,000 Earned Value $40,000 What is the cost performance index