The project team reviews identified risks and the risks response strategy. For one of the risks, the team realizes that the implementation of the risk response would generate another risk. This new risk is which of the following types of risk?

🎲 Try a Random Question  |  Total Questions in Quiz: 518  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CA0-001 PMI Practice Test — practice the complete quiz, review flashcards, or try a random question.


The project team reviews identified risks and the risks response strategy. For one of the risks, the team realizes that the implementation of the risk response would generate another risk. This new risk is which of the following types of risk?