During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.

🎲 Try a Random Question  |  Total Questions in Quiz: 371  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CAPM (Certified Associate in Project Management) Exam — practice the complete quiz, review flashcards, or try a random question.


During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.