The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: -Actual cost = $50,000 -Plan cost = $45,000 -Earned value = $40,000 What is the cost performance index?

🎲 Try a Random Question  |  Total Questions in Quiz: 371  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CAPM (Certified Associate in Project Management) Exam — practice the complete quiz, review flashcards, or try a random question.


The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: -Actual cost = $50,000 -Plan cost = $45,000 -Earned value = $40,000 What is the cost performance index?