Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

🎲 Try a Random Question  |  Total Questions in Quiz: 368  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CAPM Practice Exam — practice the complete quiz, review flashcards, or try a random question.


Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?