This matrix is used in Perform Qualitative Risk Analysis to conduct risk rating based on their probability of occurrence and impacts. It only results in a classification of high risk - moderate risk and low risk; and does not support to calculation of the probability of achieving the project target.

🎲 Try a Random Question  |  Total Questions in Quiz: 56  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CAPM Test #2 — practice the complete quiz, review flashcards, or try a random question.


1. This matrix is used in Perform Qualitative Risk Analysis to conduct risk rating based on their probability of occurrence and impacts. It only results in a classification of high risk - moderate risk and low risk; and does not support to calculation of the probability of achieving the project target.