What is the total float of the critical path?

🎲 Try a Random Question  |  Total Questions in Quiz: 648  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-100 Certified Associate Project Management Practice Exam 2 — practice the complete quiz, review flashcards, or try a random question.


What is the total float of the critical path?