The project manager decides to conduct a meeting with the team and management after a new risk has been identified. After the meeting, the decision is to allow the risk to occur. This is an example of which type of risk response strategy?

🎲 Try a Random Question  |  Total Questions in Quiz: 514  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-100 Certified Associate Project Management Practice Exam — practice the complete quiz, review flashcards, or try a random question.


The project manager decides to conduct a meeting with the team and management after a new risk has been identified. After the meeting, the decision is to allow the risk to occur. This is an example of which type of risk response strategy?