Mark works as a project manager of the NNH project. In this project, he has created a contingency response that the cost performance index should be less than 0.91. The NHH project has a budget at completion of $950,000 and is 43 percent complete -though the project should be 50 percent complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is the project's cost performance index?

🎲 Try a Random Question  |  Total Questions in Quiz: 230  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-RMP: PMI Risk Management Professional — practice the complete quiz, review flashcards, or try a random question.


Mark works as a project manager of the NNH project. In this project, he has created a contingency response that the cost performance index should be less than 0.91. The NHH project has a budget at completion of $950,000 and is 43 percent complete -though the project should be 50 percent complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is the project's cost performance index?