Shawn is the project manager of the WHT Project for his company. In this project Shawn's team reports that they have found a way to complete the project work for less cost than what was originally planned. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes to the project management plan accordingly. What type of risk response has been used in this instance?

🎲 Try a Random Question  |  Total Questions in Quiz: 230  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-RMP: PMI Risk Management Professional — practice the complete quiz, review flashcards, or try a random question.


Shawn is the project manager of the WHT Project for his company. In this project Shawn's team reports that they have found a way to complete the project work for less cost than what was originally planned. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes to the project management plan accordingly. What type of risk response has been used in this instance?