Wendy is the project manager of the FBL project for your company. She has identified several risks within her project and has created a risk contingency reserve of $45,000 total. Her project is nearly complete and many of the risks have not happened in the project. What should Wendy do with the funds in the contingency reserve?

🎲 Try a Random Question  |  Total Questions in Quiz: 230  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-RMP: PMI Risk Management Professional — practice the complete quiz, review flashcards, or try a random question.


Wendy is the project manager of the FBL project for your company. She has identified several risks within her project and has created a risk contingency reserve of $45,000 total. Her project is nearly complete and many of the risks have not happened in the project. What should Wendy do with the funds in the contingency reserve?