You are the project manager of the BJA Project for your company. Management is worried about one of the identified risks in your project. The risk event has a probability of 90 percent and a cost impact of $85,000. Management and you discuss possible solutions to address the risk. You share with them that for $75,000 you can reduce the probability of the risk event to 15 percent and the impact to $25,000. This solution will add three weeks to the project schedule. Management thinks this is a good idea and they would like you to add the time and cost additions to your project plan. What type of risk response is used?

🎲 Try a Random Question  |  Total Questions in Quiz: 230  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-RMP: PMI Risk Management Professional — practice the complete quiz, review flashcards, or try a random question.


You are the project manager of the BJA Project for your company. Management is worried about one of the identified risks in your project. The risk event has a probability of 90 percent and a cost impact of $85,000. Management and you discuss possible solutions to address the risk. You share with them that for $75,000 you can reduce the probability of the risk event to 15 percent and the impact to $25,000. This solution will add three weeks to the project schedule. Management thinks this is a good idea and they would like you to add the time and cost additions to your project plan. What type of risk response is used?






ADVERTISEMENT