A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?

🎲 Try a Random Question  |  Total Questions in Quiz: 210  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-SP: PMI Scheduling Professional Exam — practice the complete quiz, review flashcards, or try a random question.


A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?