You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25 hours per work week on your project. This policy is because your organization is in a weak matrix and the project team members are on several projects at once within the organization. The 25-hour limit per resource is an example of which one of the following?

🎲 Try a Random Question  |  Total Questions in Quiz: 210  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-SP: PMI Scheduling Professional Exam — practice the complete quiz, review flashcards, or try a random question.


You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25 hours per work week on your project. This policy is because your organization is in a weak matrix and the project team members are on several projects at once within the organization. The 25-hour limit per resource is an example of which one of the following?