You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

🎲 Try a Random Question  |  Total Questions in Quiz: 210  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-SP: PMI Scheduling Professional Exam — practice the complete quiz, review flashcards, or try a random question.


You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?