You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?

🎲 Try a Random Question  |  Total Questions in Quiz: 210  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-SP: PMI Scheduling Professional Exam — practice the complete quiz, review flashcards, or try a random question.


You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?