You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start-to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?

🎲 Try a Random Question  |  Total Questions in Quiz: 210  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-SP: PMI Scheduling Professional Exam — practice the complete quiz, review flashcards, or try a random question.


You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start-to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?