David is the project manager of the HRC Project. He has identified a risk in the project, which could cause the delay in the project. David does not want this risk event to happen so he takes few actions to ensure that the risk event will not happen. These extra steps, however, cost the project an additional $10,000. What type of risk response has David adopted?

🎲 Try a Random Question  |  Total Questions in Quiz: 148  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CRISC Assessment Test — practice the complete quiz, review flashcards, or try a random question.

The CRISC certification is designed to meet the growing demand for professionals who can integrate enterprise risk management (ERM) with discrete IS control skills.


David is the project manager of the HRC Project. He has identified a risk in the project, which could cause the delay in the project. David does not want this risk event to happen so he takes few actions to ensure that the risk event will not happen. These extra steps, however, cost the project an additional $10,000. What type of risk response has David adopted?