Wendy has identified a risk event in her project that has an impact of $75,000 and a 60 percent chance of happening. Through research, her project team learns that the risk impact can actually be reduced to just $15,000 with only a ten percent chance of occurring. The proposed solution will cost $25,000. Wendy agrees to the $25,000 solution. What type of risk response is this?

🎲 Try a Random Question  |  Total Questions in Quiz: 148  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CRISC Assessment Test — practice the complete quiz, review flashcards, or try a random question.

The CRISC certification is designed to meet the growing demand for professionals who can integrate enterprise risk management (ERM) with discrete IS control skills.


Wendy has identified a risk event in her project that has an impact of $75,000 and a 60 percent chance of happening. Through research, her project team learns that the risk impact can actually be reduced to just $15,000 with only a ten percent chance of occurring. The proposed solution will cost $25,000. Wendy agrees to the $25,000 solution. What type of risk response is this?