You are the project manager of a large construction project. This project will last for 18 months and will cost $750,000 to complete. You are working with your project team, experts, and stakeholders to identify risks within the project before the project work begins. Management wants to know why you have scheduled so many risk identification meetings throughout the project rather than just initially during the project planning. What is the best reason for the duplicate risk identification sessions?

🎲 Try a Random Question  |  Total Questions in Quiz: 148  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CRISC Assessment Test — practice the complete quiz, review flashcards, or try a random question.

The CRISC certification is designed to meet the growing demand for professionals who can integrate enterprise risk management (ERM) with discrete IS control skills.


You are the project manager of a large construction project. This project will last for 18 months and will cost $750,000 to complete. You are working with your project team, experts, and stakeholders to identify risks within the project before the project work begins. Management wants to know why you have scheduled so many risk identification meetings throughout the project rather than just initially during the project planning. What is the best reason for the duplicate risk identification sessions?