If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

🎲 Try a Random Question  |  Total Questions in Quiz: 166  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Civil Engineering Practice Test: Construction Planning and Management — practice the complete quiz, review flashcards, or try a random question.

Construction planning is the specific process a construction manager uses to lay out how they will manage and execute a construction project, from building design to completion. It lists the activities and schedule for each part of the construction process.

Construction management involves planning, budgeting, coordinating, and supervising construction projects from start to finish.

A construction manager may work on various construction projects, including buildings, roads, bridges, and other structures.


If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is