The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is

🎲 Try a Random Question  |  Total Questions in Quiz: 166  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Civil Engineering Practice Test: Construction Planning and Management — practice the complete quiz, review flashcards, or try a random question.

Construction planning is the specific process a construction manager uses to lay out how they will manage and execute a construction project, from building design to completion. It lists the activities and schedule for each part of the construction process.

Construction management involves planning, budgeting, coordinating, and supervising construction projects from start to finish.

A construction manager may work on various construction projects, including buildings, roads, bridges, and other structures.


The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is