During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months. Which of the following should have occurred to prevent this issue?

🎲 Try a Random Question  |  Total Questions in Quiz: 91  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Exam PK0-004: CompTIA Project+ — practice the complete quiz, review flashcards, or try a random question.


During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months. Which of the following should have occurred to prevent this issue?