1. In the precedence diagramming method, which of the following is a logical relationship for the activities?
2. Plurality is a type of which of the following?
3. In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08, and 12. For the entire process, the goal is 10 and the standard deviation is 1. For this data set, it is correct to say that the process:
4. What is one of the objectives of project risk management?
5. _________ is always the lowest risk for the buyer if the scope of work is not well defined.
6. Which tool and technique identifies inefficient and ineffective policies, processes and procedures?
7. Which of the following is an example of a technique used in quantitative risk analysis?
8. A project team is in which of the following processes when they finalize all activities across all of the management process groups to formally complete the project?
9. You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing him or her of your decisions. Which type of organizational structure are you working in?
10. Which of the following is an output of the Estimate Activity Resources process?
11. If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?
12. The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for the project. What is the actual status of this project?
13. Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days. What should be your concern?
14. A Risk Register is a part of the ________.
15. You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?
16. Which of the following is TRUE about most project life cycles?
17. Project team members begin to address the project work and technical decisions. The project team is in which of the following stages of team development?
18. At what point in a project do you have the highest probability that it will fail?
19. If a project with a CPI of 0.8, what you tell?
20. Create Procurement document is done in _______.
21. What cost control technique is used to compare actual project performance to planned or expected performance?
22. What causes replanning of the project scope?
23. You are project manager of a project, which of the following is not your responsibility?
24. Which of the following provides a standardized, effective, and efficient way to centrally manage approved changes and baselines within a project?
25. During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.