You are in charge of a software project and you are almost 40% complete.The project stakeholders want a performance report to date.You had planned to use Earned Value Management methodology.You come up with the following numbers: EV = 100 AC = 300 PV = 150 BAC = 600 You and your team have faced numerous issues till now . However you choose to ignore the current work performance and decide to go with what was originally planned. Based on this information what would be the EAC for the project ?

🎲 Try a Random Question  |  Total Questions in Quiz: 20  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Project Management: Executing, Controlling, Managing a Project — practice the complete quiz, review flashcards, or try a random question.


You are in charge of a software project and you are almost 40% complete.The project stakeholders want a performance report to date.You had planned to use Earned Value Management methodology.You come up with the following numbers: EV = 100 AC = 300 PV = 150 BAC = 600 You and your team have faced numerous issues till now . However you choose to ignore the current work performance and decide to go with what was originally planned. Based on this information what would be the EAC for the project ?