1. Why does activities on critical path of a CPM network are called critical
2. Latest starting date for an activity is estimated using
3. Which of the following is a good condition for top-down estimating?
4. An activity on the CPM network has Early start on 8th day, Early Finish is 14th day, Late start is 10th day and Late finish is 16th day. What is the float available for this activity?
5. A projeect has three independent critical paths A (Having maximum no. of activities), B(Using maximum rsources) and C(Having maximum crashing cost). To reduce the project length, we have to crash
6. In PERT, if the pessimistic time were 14 weeks, the optimistic time were 8 weeks, and the most likely time were 11 weeks,
7. An activity considered for PERT scheduling has estimated durations as, optimistic 5 days, pessimistic 10 days, and most likely 6 days. What is the expected time duration for this activity?
8. The lowest element in the hierarchical breakdown of the WBS is
9. The project has critical path duration of 21 weeks and the variance of critical path is 3.44. What is completion time corresponding to 98% probability if Z value is 2.06 for 98% probability?
10. Information to develop a project network is collected from the
11. Part of a project is to '
12. In PERT, if the pessimistic time were 14 weeks, the optimistic time were 8 weeks, and the most likely time were 11 weeks,
13. Select the correct statement from the following
14. A critical path of a project has four independent activities A(5,1.666), B(15,1.666), D(4,0.444) and E(5,0). The bracketed terms are (expected time, standard deviation) The expected duration of critical path is '
15. The project has critical path duration of 21 weeks and the variance of critical path is 3.44. What is completion time corresponding to 98% probability if Z value is 2.06 for 98% probability?
16. If an activity with free slack time of 2 weeks is delayed by 1 week
17. Why does activities on critical path of a CPM network are called critical
18. An activity considered for PERT scheduling has estimated durations as, optimistic 5 days, pessimistic 10 days, and most likely 6 days. What is the expected time duration for this activity?
19. Part of a project is to '
20. If an activity with free slack time of 2 weeks is delayed by 1 week