A company undertook to pay contract for a building for ?90 lakhs. As on 31.03.2017, it incurred a cost of ?15 lakhs and expects that there will be ?68 lakhs more for completing the building. It has received ?12 lakhs as progress payment. What is the degree of completion?

🎲 Try a Random Question  |  Total Questions in Quiz: 106  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
CMA Final Exam: Corporate Financial Reporting — practice the complete quiz, review flashcards, or try a random question.

The syllabus (with weightage):
A. GAAP and Accounting Standards 20%
B. Accounting of Business Combinations & Restructuring 20%
C. Consolidated Financial Statements 20%
D. Developments in Financial Reporting 25%
E. Government Accounting in India 15%


A company undertook to pay contract for a building for ?90 lakhs. As on 31.03.2017, it incurred a cost of ?15 lakhs and expects that there will be ?68 lakhs more for completing the building. It has received ?12 lakhs as progress payment. What is the degree of completion?






ADVERTISEMENT