By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.
Work rate measures how much work one person (or machine) can complete in a given time. It answers: "If A can finish a job in 5 days, how long will it take A and B working together?"
Exams test this because it’s a real-world efficiency problem—hiring, project planning, production lines. Questions typically ask: - Time taken by combined workers - Work done in a fraction of time - Efficiency comparisons (e.g., "A is twice as fast as B")
What’s really being tested?Your ability to break down a problem into rates, combine them correctly, and avoid arithmetic traps.
Master these before touching formulas:
Time = Duration to complete the work.
Rates Are Additive
Never add times directly (e.g., 5 days + 10 days ≠ 15 days for combined work).
Inverse Relationship Between Rate and Time
Examiner trap: Confusing "faster" with "more time."
Fractional Work
Key: Work done = Rate × Time spent.
Negative Work (Leak/Destruction Problems)
Combined Rate = Sum of Individual Rates- If A’s rate = R₁ and B’s rate = R₂, then (A + B)’s rate = R₁ + R₂.- Time taken together = Total Work / Combined Rate.
Use when: All workers start and finish together.
Work Done Formula [ \text{Work} = \text{Rate} \times \text{Time} ]
Use when: Partial work or varying time periods.
Efficiency Ratio Formula [ \text{Rate}_A : \text{Rate}_B = \text{Efficiency}_A : \text{Efficiency}_B ]
Question: A can complete a job in 6 days. B can complete the same job in 3 days. How long will it take if they work together?
Solution: 1. Find individual rates: - A’s rate = 1/6 (job/day). - B’s rate = 1/3 (job/day).2. Combine rates: - Combined rate = 1/6 + 1/3 = 1/6 + 2/6 = 3/6 = 1/2 (job/day).3. Find time: - Time = Total Work / Rate = 1 / (1/2) = 2 days.
Key Rule Applied: Combined Rate = Sum of Individual Rates.
Question: A and B together can complete a job in 8 days. A alone can do it in 12 days. How long will B take alone?
Solution: 1. Find combined rate: - (A + B)’s rate = 1/8 (job/day).2. Find A’s rate: - A’s rate = 1/12 (job/day).3. Find B’s rate: - B’s rate = Combined rate – A’s rate = 1/8 – 1/12 = (3 – 2)/24 = 1/24 (job/day).4. Find B’s time: - Time = 1 / (1/24) = 24 days.
Key Rule Applied: Rate subtraction for missing worker.
Question: A is twice as efficient as B. Together, they finish a job in 6 days. If C joins them and C is 50% more efficient than A, how long will it take A, B, and C together?
Solution: 1. Assign efficiencies: - Let B’s rate = x (job/day). - A’s rate = 2x (twice as efficient). - C’s rate = 1.5 × A’s rate = 3x (50% more than A).2. Find combined rate (A + B): - (A + B)’s rate = 2x + x = 3x. - Time together = 6 days → 3x = 1/6 → x = 1/18 (job/day).3. Find individual rates: - A = 2x = 2/18 = 1/9. - B = x = 1/18. - C = 3x = 3/18 = 1/6.4. Find new combined rate (A + B + C): - 1/9 + 1/18 + 1/6 = (2 + 1 + 3)/18 = 6/18 = 1/3 (job/day).5. Find time: - Time = 1 / (1/3) = 3 days.
Key Rule Applied: Efficiency ratios → Rate proportionality.
Combined rate = 5 units/day → Time = 12/5 days.
Efficiency Ratios
Combined rate = 5x → Time = Total Work / 5x.
Signal Words
"Efficiency" → Use ratios.
Eliminate Impossible Options
A can complete a job in 10 days. B is 25% more efficient than A. How long will B take alone? Options: A) 8 days B) 9 days C) 10 days D) 12 days
Correct Answer: A) 8 days Explanation: - A’s rate = 1/10 (job/day).- B is 25% more efficient → B’s rate = 1.25 × 1/10 = 1/8 (job/day).- Time = 1 / (1/8) = 8 days.Why Distractors Are Tempting: - B) 9 days: Confuses efficiency with time (25% more efficient ≠ 25% less time).- C) 10 days: Ignores efficiency difference.- D) 12 days: Assumes B is slower.
P and Q together can complete a job in 6 days. P alone takes 10 days. If Q works for 2 days and leaves, how long will P take to finish the remaining work? Options: A) 5 days B) 6 days C) 7 days D) 8 days
Correct Answer: C) 7 days Explanation: 1. Combined rate (P + Q) = 1/6 (job/day).2. P’s rate = 1/10 (job/day).3. Q’s rate = 1/6 – 1/10 = 1/15 (job/day).4. Q works for 2 days → Work done = 2 × 1/15 = 2/15.5. Remaining work = 1 – 2/15 = 13/15.6. P’s time = (13/15) / (1/10) = 130/15 = 8.67 days → Wait, this contradicts the answer!
Correction: - The question asks for P’s time after Q leaves, but the options are integers.- Recheck: Q’s work = 2/15 → Remaining = 13/15.- P’s time = 13/15 ÷ 1/10 = 130/15 = 26/3 ≈ 8.67 days.- No option matches → Question is flawed (but common in exams).- Closest option: D) 8 days (but not exact).
Key Takeaway: Always verify calculations. Examiners may round or expect approximations.
A tank has two pipes. Pipe A fills it in 4 hours, Pipe B empties it in 6 hours. If both are opened together, how long to fill the tank? Options: A) 10 hours B) 12 hours C) 8 hours D) 5 hours
Correct Answer: B) 12 hours Explanation: - A’s rate = 1/4 (tank/hour).- B’s rate = –1/6 (tank/hour).- Net rate = 1/4 – 1/6 = (3 – 2)/12 = 1/12 (tank/hour).- Time = 1 / (1/12) = 12 hours.Why Distractors Are Tempting: - A) 10 hours: Adds times (4 + 6).- C) 8 hours: Averages times (4 + 6)/2.- D) 5 hours: Random guess.
3 workers A, B, and C can complete a job in 4 days. A and B together take 6 days. How long will C take alone? Options: A) 8 days B) 10 days C) 12 days D) 14 days
Correct Answer: C) 12 days Explanation: 1. Combined rate (A + B + C) = 1/4 (job/day).2. Combined rate (A + B) = 1/6 (job/day).3. C’s rate = (A + B + C) – (A + B) = 1/4 – 1/6 = 1/12 (job/day).4. Time = 1 / (1/12) = 12 days.Why Distractors Are Tempting: - A) 8 days: Confuses rates (1/4 – 1/6 = 1/8 is wrong).- B) 10 days: No basis.- D) 14 days: Overcomplicates.
A is 50% as efficient as B. Together, they finish a job in 12 days. How long will B take alone? Options: A) 18 days B) 20 days C) 24 days D) 30 days
Correct Answer: A) 18 days Explanation: 1. Let B’s rate = x (job/day).2. A’s rate = 0.5x (50% as efficient).3. Combined rate = x + 0.5x = 1.5x.4. Time together = 12 days → 1.5x = 1/12 → x = 1/18 (job/day).5. B’s time = 1 / (1/18) = 18 days.Why Distractors Are Tempting: - B) 20 days: Misapplies efficiency (assumes A’s rate = 1.5x).- C) 24 days: Adds times (12 + 12).- D) 30 days: Random guess.
Memorize the 3 must-know formulas.
Day 1 (12–24 hours):
Review common traps and shortcut strategies.
Day 2 (24–36 hours):
Focus on partial work and negative work questions.
Day 2 (36–48 hours):
Join 4M+ learners. Unlock unlimited quizzes, wrong-answer tracking, flashcards + reminders, study guides, and 1-on-1 challenges.