CAPM (Certified Associate in Project Management) Exam
Fast practice, instant feedback. Timer auto-submits when time’s up.
Avg score: 69% Most missed: “Draw the precedence diagram for the dependencies and activity times below to ans…”
CAPM (Certified Associate in Project Management) Exam
Time left 00:00
25 Questions

1. Which is an input to the Scope Verification Process?
2. A project manager convenes a meeting to determine why the time to produce one product according to specifications has increased from one day to three days over the past month. Which tool or technique is used in this case?
3. What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
4. Which process group defines the course of action required to attain the objectives that the project was undertaken to achieve?
5. Cost baseline is an output of which of the following processes?
6. If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?
7. Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?
8. Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
9. Which of the following is an example of contract administration?
10. Which of the following is an input to the Direct and Manage Project Work Process?
11. Which of the following is a strategy to deal with positive risks or opportunities?
12. What cost control technique is used to compare actual project performance to planned or expected performance?
13. Which technique is utilized in the Schedule Control process?
14. Initiating, Planning, Executing, Monitoring and Controlling and Closing are called:
15. Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?
16. Which process group establishes the total scope of a project?
17. What scope definition technique is used to generate different approaches to execute and perform the work of the project?
18. Analogous Cost Estimating relies on which of the following techniques?
19. Which of the following is contained within the communications management plan?
20. What does a SPI value greater than 1.0 indicate?
21. Who decides buyer and seller roles in a teaming agreement?
22. The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for the project. What is the actual status of this project?
23. Which is the document that presents a hierarchical project organization?
24. What is Project Portfolio Management?
25. Which tool or technique uses the 80/20 principle?