1. Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this project, though he is supposed to be at his second milestone, which accounts for half of the project completion. There have been some errors in the project, which have caused Allen to spend $2,093,754. What is this project's schedule variance?
2. You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?
3. Yolanda is the project manager for her organization. She is creating a performance report for her sponsor. Typically, the performance report includes all of the following factors except for which one?
4. Your organization wants to start a new project. The study shows that the new project will save organization approximately $200,000 per year. Now it is required to move forward with the project. Which of the following documents will define the project justification?
5. Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project -including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?
6. You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?
7. Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 90 percent done by this date. She has spent $490,000 to date. What should Billy report as her cost performance index (CPI)for this project?
8. You work as a project manager for BlueWell Inc. By referring to the figure given below, you along with your project team is calculating the latest completion of an activity. What is the latest your project team can complete Activity I?
9. Jeff is the project manager of the GHY Project for his organization. He has created the project network diagram as shown in the figure: Management is reviewing the network diagram, and they are concerned about the latest date that Activity I can finish. What is the latest day Activity I can finish without affecting the project end date?
10. Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?
11. You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?
12. You are the project manager of the NHQ project. This project is currently running about 15 percent behind schedule and the management has asked you to rectify the problem. You have elected to crash the project. What does this term mean?
13. You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?
14. What is the formula to find the schedule performance index?
15. You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier and a scope of work description for each activity in the activity list. Why is this information needed?
16. You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?
17. You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410 What is the schedule variance (SV) of the project at the current point of time?
18. What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
19. Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide activity duration estimate for an activity. Beth provides Della the following estimate chart: What will be the activity duration according to the PERT three-point analysis?
20. You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are up posed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule variance?
21. You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?
22. Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?
23. Kenny is the project manager for the NHQ organization. She is creating the project duration estimates. She has stressed to her project team that they will need to create accurate and reliable project duration estimates without padding their estimates for errors or risks. Kenny is also relying on historical information to help her predict the duration of the project work. Jennifer, one of the project team members, wants to know how Kenny will account for the certain-to-happen errors and delays in the project schedule. What approach should Kenny use in the project?
24. John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.
25. You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?