1. What cost estimating approach uses the work breakdown structure to create a cost estimate?
2. You are the program manager for your organization. This program will last for two years and has eight projects. The cost of your program is $4 million and there are some risk concerns that may affect the overall cost of the program. Management is concerned with how long it will take the program to reach the management horizon. What is management horizon also known as?
3. If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
4. What project management term would you associated with a predetermined budget you’re your program?
5. You are the program manager for your organization and you're dealing with several issues about the materials used in the program. Right now, the issues have been assigned to issue owners for resolution in ten days. In the interim, what should you do with the issues?
6. Which one of the following is not an output of the direct and manage program execution process?
7. You are the program manager for your organization and are planning the composition of the project team. In your organization resources are used from throughout the company and may serve on more than one project. While you, the program manager, will have most of the authority on the program you want the project managers to have authority over the project decisions. What type of an organizational structure does your organization have?
8. Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances. Mary Anne has decided, however, that her program needs to be terminated. Which one of the following is a likely reason why the project should be terminated?
9. Molly is the program manager for her organization. She is creating a document that defines the benefits the program will create for her organization once the program has been completed. What document is Molly writing?
10. Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?
11. Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?
12. Which one of the following is NOT a component of the risk monitoring and controlling process?
13. Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?
14. You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?
15. You are the program manager for the BHN Program. Your program has 122 stakeholders that you'll need to plan to communicate with. Considering the size of the program how many communication channels do you have in this program?
16. In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?
17. Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?
18. Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of the following is the best chart for Gina in this situation?
19. You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this scenario?
20. Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?
21. Julie is the project manager of the NHQ Project. She and her project team have successfully finished the project and the customers have signed the project closure agreement. Julie has compiled all of the project records and the project's lessons learned documentation. What should Julie do with the project's lessons learned documentation?
22. Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?
23. You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?
24. At what point in the project is the risk of failing to achieve the project objectives the greatest?
25. You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?