If the project is falling behind schedule, you can think about ways to get it back on track. You might add people to a task to try to finish it more quickly, but what is the downside of this?

🎲 Try a Random Question  |  Total Questions in Quiz: 32  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Microsoft Project: Small Projects — practice the complete quiz, review flashcards, or try a random question.


1. If the project is falling behind schedule, you can think about ways to get it back on track. You might add people to a task to try to finish it more quickly, but what is the downside of this?