Fatskills
Practice. Master. Repeat.
Study Guide: Operations Management 101: Process Design and Analysis Littles Law WIP Throughput Cycle Time
Source: https://www.fatskills.com/nasm/chapter/operations-management-opsmgmt-process-design-and-analysis-littles-law-wip-throughput-cycle-time

Operations Management 101: Process Design and Analysis Littles Law WIP Throughput Cycle Time

By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.

⏱️ ~3 min read

What This Is

Little's Law is a fundamental concept in operations management that relates the amount of work in progress (WIP) to the throughput and cycle time of a production system. It is essential in understanding the dynamics of production and inventory systems. For example, consider a manufacturing line producing 100 units per hour with an average cycle time of 2 hours. According to Little's Law, the WIP would be 200 units (100 units/hour × 2 hours).

Key Formulas & Frameworks

  • Little's Law: WIP = Throughput × Cycle Time where WIP = work in progress, Throughput = units produced per unit of time, and Cycle Time = average time a unit spends in the system.
  • Throughput = Output / Time where Output = units produced and Time = time period.
  • Cycle Time = Time / Units where Time = time period and Units = units produced.
  • Takt Time = Throughput / Demand where Demand = customer demand per unit of time.
  • Lead Time = Cycle Time + Queue Time where Queue Time = time a unit spends waiting in the system.
  • WIP Inventory = Throughput × Cycle Time where WIP Inventory = average inventory level.
  • Inventory Turnover = Throughput / Inventory where Inventory = average inventory level.
  • Cycle Time Variance = (Cycle Time - Target Cycle Time) / Target Cycle Time where Target Cycle Time = desired cycle time.

Step-by-Step Application

  1. Calculate Throughput: Determine the production rate (units per hour) and the time period (hours) to calculate the throughput.
  2. Determine Cycle Time: Measure the average time a unit spends in the system or calculate it using the formula Cycle Time = Time / Units.
  3. Calculate WIP: Use Little's Law to calculate the WIP by multiplying the throughput and cycle time.
  4. Analyze Lead Time: Calculate the lead time by adding the cycle time and queue time to understand the total time a unit spends in the system.
  5. Optimize Cycle Time: Use the cycle time variance formula to identify areas for improvement and optimize the cycle time to reduce waste and increase efficiency.
  6. Monitor Inventory: Use the inventory turnover formula to monitor the inventory level and adjust the production rate or inventory level accordingly.

Common Mistakes

  • Mistake: Confusing throughput with production rate.
  • Correction: Throughput is the rate at which units are produced and delivered to customers, while production rate is the rate at which units are produced.
  • Mistake: Assuming cycle time is the same as lead time.
  • Correction: Cycle time is the average time a unit spends in the system, while lead time is the total time a unit spends in the system, including waiting time.
  • Mistake: Not considering queue time when calculating lead time.
  • Correction: Queue time is an essential component of lead time and should be included in the calculation.

Exam / Certification Tips

  • Be aware of the difference between push and pull systems: Push systems produce units based on a forecast, while pull systems produce units based on customer demand.
  • Understand the distinction between Cp and Cpk: Cp is the process capability index, while Cpk is the process capability index with a shift.
  • Know the difference between planned and actual capacity: Planned capacity is the designed capacity, while actual capacity is the actual production rate.

Quick Practice Problem

A manufacturing line produces 120 units per hour with an average cycle time of 1.5 hours. What is the WIP?

Answer: 180 units (120 units/hour × 1.5 hours) Explanation: Using Little's Law, we can calculate the WIP by multiplying the throughput and cycle time.

Last-Minute Cram Sheet

  • Little's Law: WIP = Throughput × Cycle Time
  • Throughput = Output / Time
  • Cycle Time = Time / Units
  • Takt Time = Throughput / Demand
  • Lead Time = Cycle Time + Queue Time
  • WIP Inventory = Throughput × Cycle Time
  • Inventory Turnover = Throughput / Inventory
  • Cycle Time Variance = (Cycle Time - Target Cycle Time) / Target Cycle Time
  • ⚠️ Throughput ≠ Production Rate
  • ⚠️ Cycle Time ≠ Lead Time
  • ⚠️ Queue Time is part of Lead Time