By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.
Earned Value Management (EVM) is a project management technique that measures project performance by comparing actual progress to planned progress. It helps organizations track costs, schedule, and performance by calculating three key metrics: Planned Value (PV), Earned Value (EV), and Actual Cost (AC). EVM is widely used in construction, aerospace, and IT projects, but its principles can be applied to any operation where projects are executed.
For example, consider a construction project where the planned value of a building is $1 million, and the actual cost incurred so far is $600,000. If 40% of the work is completed, the earned value would be $400,000 (40% of $1 million). This indicates that the project is under budget and ahead of schedule.
A construction project has a planned value of $500,000 and an actual cost of $300,000. If 60% of the work is completed, what is the earned value?
Answer: $300,000 (60% of $500,000) Explanation: The earned value is the budgeted cost of work performed to date, which is 60% of the planned value.
Join 4M+ learners. Unlock unlimited quizzes, wrong-answer tracking, flashcards + reminders, study guides, and 1-on-1 challenges.