A firm uses the pure chase strategy of aggregate planning. It produced 1000 units in the last period. Demand in the next period is estimated at 800, and demand over the next six periods (its aggregate planning horizon) is estimated to average 900 units. Which of the following tactics would be most representative of following a chase strategy?

🎲 Try a Random Question  |  Total Questions in Quiz: 71  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Operations Management 101 Practice Test: Aggregate Scheduling — practice the complete quiz, review flashcards, or try a random question.

Aggregate scheduling is a part of aggregate planning, which is the process of creating an approximate schedule for how an organization will operate over a period of time, typically 3–18 months. Aggregate planning covers all production activities at a facility, not just individual production runs or the manufacture of individual products. The goal of aggregate planning is to help a business fulfill forecasted demand at minimal cost.  Aggregate planning helps management decide when and how much to procure materials and other resources. It also helps determine: Outsourcing, Subcontracting,... Show more

A firm uses the pure chase strategy of aggregate planning. It produced 1000 units in the last period. Demand in the next period is estimated at 800, and demand over the next six periods (its aggregate planning horizon) is estimated to average 900 units. Which of the following tactics would be most representative of following a chase strategy?