A production line is to be designed to make 500 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The factory operates 750 minutes per day. What is the required cycle time for this assembly line?

🎲 Try a Random Question  |  Total Questions in Quiz: 90  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Operations Management 101 Practice Test: Layout Decisions — practice the complete quiz, review flashcards, or try a random question.

Layout decisions are a key part of operations management and can have strategic implications. Layout decisions can affect an organization's competitive priorities in terms of: Capacity, Processes, Flexibility, Cost, Quality of work life, Customer contact, and Image.  Here are some types of layout decisions: Process layout: This layout is used when a company manufactures a low volume of products with a high variety. In this layout, workstations or departments are grouped by function. For example, in a retail store, all grocery functions would be arranged in one place. Product layout: This... Show more

A production line is to be designed to make 500 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The factory operates 750 minutes per day. What is the required cycle time for this assembly line?