A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less?

🎲 Try a Random Question  |  Total Questions in Quiz: 72  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Operations Management 101 Practice Test: Managing Projects — practice the complete quiz, review flashcards, or try a random question.


A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less?