A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

🎲 Try a Random Question  |  Total Questions in Quiz: 72  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Operations Management 101 Practice Test: Managing Projects — practice the complete quiz, review flashcards, or try a random question.


A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?