The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.

🎲 Try a Random Question  |  Total Questions in Quiz: 72  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Operations Management 101 Practice Test: Managing Projects — practice the complete quiz, review flashcards, or try a random question.


The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.