Real 196 The project manager for XYZ stationers is sequencing the activities for the project to set up a new office. It is known from knowledge of best practices that it is better to wait for the painters to finish painting the walls before the new floors are installed. This is an example of which of the following types of dependency?

🎲 Try a Random Question  |  Total Questions in Quiz: 301  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI Project Management Professional Exam — practice the complete quiz, review flashcards, or try a random question.


Real 196 The project manager for XYZ stationers is sequencing the activities for the project to set up a new office. It is known from knowledge of best practices that it is better to wait for the painters to finish painting the walls before the new floors are installed. This is an example of which of the following types of dependency?