The Project Budget Is Set At $150 - 000the Project Duration Is Planned To Be One Yearat The Completion Of Week 16 Of The Project - The Following Information Is Collected Actual Cost = $50 - 0 - Plan Cost = $45 - 0 - Earned Value = $40 - 000what Is The Cost Performance Index