NEC-Electrician: Commercial Load Calculation Overview — Flashcards | National Electrical Code (NEC) exam | FatSkills

NEC-Electrician: Commercial Load Calculation Overview — Flashcards

Fast review mode: answers are shown by default so you can skim quickly. Hide them if you want to self-test.

Commercial load calculation sizes feeders/services for non-dwelling occupancies. It is driven by: connected loads, continuous loads (125% rule for OCPD/conductors), demand factors for lighting/receptacles where permitted, motor calculations (largest motor at 125% plus others), and HVAC/heat based on operating conditions.

continuous load 125%, demand factors, motor contribution, largest motor at 125%, non-dwelling.

Worked example (continuous load concept):
If a lighting load is continuous (expected 3 hours or more), you often size the circuit at 125% of that load for conductor/OCPD sizing purposes (exam staple).

1 of 8 Ready
A “continuous load” is commonly defined as a load expected to run for:
3 hours or more
Shortcuts
Prev Space Show / hide Next
Turn this into a study set.
Sign in with Google to save tricky questions to your reminder list and resume on any device.
Sign in with Google Free • no extra password